President/Building Project Report – Submitted by charles suhr Next meeting on n/a. The building permit for Phase 2 has been issued. Work is anticipated to start by the week of October 26th. Please review the updated scope and costing of the Phase 2 project. Campbell contract price now totals $1,010,925 ($137,613.64 for phase 1, and $873,312.00 for phase 2). We will go over these numbers during the meeting. CMS

By | September 8, 2020 Council Reports

President/Building Project Report – Submitted by charles suhr Next meeting on n/a. Phase 1 improvements for the second floor-preschool area are nearly complete. Phase 2 plans have been submitted to Camp Hill Boro for code review and are still under review. Hope to have comments back from codes in the next week or so.